Redevelopment lease renewals
A recent case decided by the High Court will (if not overturned on appeal) have potential implications for some commercial tenants seeking renewals of their tenancies.
The case of S Franses Ltd. v The Cavendish Hotel (London) Ltd. involved a dealer in textiles that occupies areas in the ground and basement floors of London’s Cavendish Hotel and which wishes to renew its tenancy relying on the security given by the Landlord and Tenant Act 1954, which gives such tenants the right to renew their tenancies except in certain circumstances.
One of the circumstances in which a renewal can be refused is if the landlord wishes to demolish or reconstruct the premises occupied by the tenant. The landlord (which runs the hotel) claimed that it did and it could not carry out the works it wishes to undertake without gaining possession of the tenanted premises.
What made this somewhat different from the norm was that it appeared that the landlord would not have wanted to carry out the work it used to justify the termination of the tenancy if the tenant had agreed willingly to vacate the building. The tenant claimed that the landlord’s motivation was purely to evict it and therefore the landlord should not be allowed to terminate the lease.
The High Court’s judgment was that there was one core issue: did the landlord really intend to carry out the work? That alone would decide the matter. The landlord’s motivation for doing the work was not in point.
The case isn’t quite over. The County Court has to decide on the extent to which the work specified might be able to be done leaving the tenant in place and also the timescale in which the work should be commenced.
However, it is quite feasible that landlords seeking to remove protected commercial tenants may, if the premises offer a financially suitable redevelopment opportunity, use the works primarily as a device to remove an unwanted tenant.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.
UKCW London to tackle sector’s most pressing issues
AI and skills development, ecology and the environment, policy and planning and more.
Managing building safety risks
Across an existing residential portfolio; a client's perspective.
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.
Some of the articles relating to water, here to browse. Any missing?
Recognisable Gothic characters, designed to dramatically spout water away from buildings.
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.